The normal use of steel silo is inseparable from daily maintenance and overhaul, the current types of steel silo, according to the structural form is divided into: welded steel warehouse, galvanized plate spiral coil plate warehouse, galvanized plate bolt assembly warehouse. Steel plate grain silo is widely used, after the construction of steel plate grain silo is completed and put into use, it is necessary to master the correct use and maintenance, overhaul and other knowledge of steel plate grain silo, timely maintenance and correct operation of steel plate grain silo can extend the service life of steel plate grain silo.
The normal use of steel silos is inseparable from daily maintenance, maintenance and overhaul, and it is strictly prohibited to add additional facilities to steel silos without authorization to prevent accidents.
1, Eccentric loading and unloading are not allowed during use, and direct drainage of the warehouse wall is strictly prohibited. Attention should be paid to the self-sealing inspection of the steel bin, and attention should be paid to checking the connection between the steel bin and the embedded parts to prevent rain from entering the steel bin.
2, Before the arrival of the rainy season every year, the construction party should carefully check the corrosion of the steel warehouse, and regularly carry out anti-corrosion treatment.
The maintenance of the steel warehouse needs to be checked once a month, check the surface rust and its sealing, etc., and maintain the problem in time.
3, It is necessary to often check whether there is local deformation of the steel warehouse wall, and often check the tightness of the steel warehouse after unloading the empty warehouse, or whether there are cracks and other phenomena, and maintain, repair and maintenance according to the actual situation.
4, If the whole steel plate warehouse is unloaded, it is necessary to regularly check the connection parts of the bucket, welding, the surface of the bucket plate, etc., if abnormal conditions such as welding deformation and cracking occur, the feeding should be stopped to avoid accidents.
5, Because the working condition of the steel plate silo is alternating load, the welding seam of the steel plate silo body is checked every six months, the deformation of the welding seam should be corrected and repaired, and the corrosion treatment should be carried out in time.
6, In addition, the air pressure entering the steel plate bin can not be too large, must ensure that the top of the warehouse breathing valve unblocked, install vacuum pressure release valve when necessary, the filter cloth in the bin top dust collector can not collect dust, regularly check whether the top of the warehouse ventilation hole is unblocked, prohibit excessive pressure in the steel plate bin, to prevent the weak strength of the burst.